• The Portland Water Bureau’s contractor for the project, James W. Fowler Co. (JWF) will  continue with exploratory excavation (“potholing”) in each of the Work Areas in November. There will be a short disruption of traffic flow in some of the areas, primarily along SE Lincoln Street and SE Lincoln Drive.
  • JWF will continue pipe work in Work Areas 9 and 11 ,which involves the capping of outlet pipes and placing screens on inlet pipes in both cells of Reservoir 6 and in Reservoir 1. All the work will take place in the reservoirs and in the gatehouses.
  • JWF will set up its construction storage modulerand staging area at the south entrance to the park, adjacent to SE Lincoln Street.
  • Portland Water Bureau Construction and Maintenance crews will finish work in Work Area 8, which is at the bottom of the stairs between Reservoir 6 and SE 60th Avenue.
  • Work inside the underground vault located on the service road between Reservoir 5 and the dog park will likely begin.
  • Excavation will likely occur on and around the vaults in Work  Area7, which is located between the bottom of the steps from Reservoir 5 to the top of the steps leading down to Reservoir 6.